Poisoned groundwater was detected near top oligarch’s waste processor
According to local civil society groups, the company's site pollutes a nature reserve and endangers the drinking water of nearby settlements.
According to local civil society groups, the company's site pollutes a nature reserve and endangers the drinking water of nearby settlements.
According to documents and video recordings obtained by Átlátszó, a fire and explosion occurred during testing at the SK Battery Manufacturing Kft. factory in Komárom.
Telex cites leaked internal documents showing that shortly before Átlátszó was targeted by the Sovereignty Protection Office, the management of the Samsung battery factory was discussing ways to shot down our investigations into their pollution.
While the Ministry of Agriculture says everything is fine with Hungary’s forests, large sections of protected forests are being cut down to fuel biomass power plants.
The court's decision has been illegally overruled by the government, which has ruled that the factory can continue to operate even without an environmental permit.
The Budapest Regional Court annulled the environmental permit of the Samsung battery factory of Göd, ruling that the permit was issued illegally.
In a video report, we took a look at how water projects carried out by Mészáros and Mészáros Zrt. are progressing in Göd, Iváncsa and Debrecen, the sites of the largest Hungarian battery factories.
Lőrinc Mészáros’s company continues to receive billions in public money to build waterworks for the battery plant which they were supposed to complete a year ago.
Locals protested against the plant's operation and expansion in early May with a public forum and a petition with thousands of signatures.
Mayors and residents in the area are prepared to physically resist to stop the project. On-the-spot report from Bosnia and Herzegovina.
For nearly two years, 1,700 tonnes of hazardous battery waste, stinking of solvents, were stored in unprotected warehouses on the site of the former Abasár barracks, while the authorities issued unsuccessful notices to remove the waste.
The https://english.atlatszo.hu use cookies to track and profile customers such as action tags and pixel tracking on our website to assist our marketing. On our website we use technical, analytical, marketing and preference cookies. These are necessary for our site to work properly and to give us inforamation about how our site is used. See Cookies Policy