Minister Péter Szijjártó lost in the Rosatom-Siemens Energy-Framatome Bermuda Triangle
If the minister knew about this, he kept it quiet, if he did not know about it, then the government is following the events with a considerable lag.
If the minister knew about this, he kept it quiet, if he did not know about it, then the government is following the events with a considerable lag.
"Something happened" at the Paks II nuclear plant construction site, but the various parties involved in the construction offered contradictory statements.
The Paks Nuclear Power Plant has persistently strived to conceal the data measured by the line of buoys we found in the Danube a year and a half ago near the power plant.
According to the authority, the impacts of the continued operation of Paks NPP could affect most of Europe, but only a few municipalities in Hungary.
The Hungarian Atomic Energy Authority refused to comply with our freedom of information request.
According to our on-site measurements, even the power reduction was not sufficient to allow the plant to maintain the 30 degree heat limit in the river Danube.
Four years ago, and now again, we measured higher water temperatures in the Danube at the Paks Nuclear Power Plant...
According to an official document obtained by Átlátszó, János Süli, the Hungarian minister responsible for the Paks NPP expansion, prepared...
Although the Hungarian Atomic Energy Authority (HAEA) has not yet issued the Paks II construction license but has requested further...
The site of the Paks NPP and the planned Paks II NPP are not suitable for the construction of a...
The Paks NPP and the site of the planned Paks II NPP are not suitable for the construction of a...